Successful Acceptance of Risheng Power Plant Industrial Cooling Tower Upgrade Modification Project
News
2022-05-25 12:57:48

OWNER: Shaoneng Group Shaoguan Risheng Power Plant
At the invitation of the owner, our technical team proposed a reasonable solution for the insufficient performance of the original cooling tower after field investigation. Finally, our solution stand out from a number of powerful suppliers to be the final winning scheme.

When the project was completed, NEWIN technical team carried out field and evaluation (adopt national standard and CTI CTA-105, water vapor ratio evaluation method in field test of cooling tower). The test results showed that the thermal performance of the cooling tower after modification improved 21.5% than the original, and it was reached the meeting of owner’s transformation requirements.